Current Projects
2024 Community Center ADA Upgrade
July 9,2024 Update: Concrete stairs, landing and ramp completed along with all concrete sidewalks with control and expansion joints. Tactile warning strips have been installed at the top of the stairs. Galvanized railing is on site. Lift has been inspected [...]
Wastewater Treatment Plant Disinfection and Phosphorus Removal Upgrade
June 26, 2024 Update: The bids for this project were opened on June 18th at the Town of Jay offices with several bidder in attendance. MJ's recommendations for contract awards are for General Construction - MCJ Construction, LLC for a [...]
Water District Upgrades
February 7,2025 update: Water Meter Feasibility Study - Final Draft submitted to the Town and can be seen here. October 10,2024 update: Water Meter Feasibility Study - updated draft engineering report submitted to the Town for review on 8/30/24 District [...]